39 Wicca Street, Rivervale – Project Update February 2019

Since the last project update the builder has completed the site-works and the plumbers and electricians have completed their pre-lays. This then permitted the slabs to be formed and poured. The slabs are currently curing and once the curing process has completed the bricklayers will commence.

I look forward to updating you next month, however, should you have any queries in the meantime, please do not hesitate to contact me on (08) 6144 0700 or 0451 533 440.

Regards,
Travis McKenzie

Share

[addtoany]

Read Next

Royal Commission Report

Finance

Get the latest insights and sign up 

Need more information?

Whether you’re investing, building, or need property support, we are here to guide you through every step of your property journey.