Almond Lane, Ardross – Project Update April 2016

Despite some wet weather in April good progress has been made on site.

The brickwork to the ground level of the townhouses is now complete and work has commenced on the formwork for the first floor slab. At the rear building the slab has now cured and work is underway on the brickwork of the first floor apartments.

Once this brickwork is complete, work will commence on the roof structure to the rear building with the aim of achieving roof cover before the winter months commence. We remain on track for completion in December this year and I look forward to updating you as the project progresses. If you have any questions, please don’t hesitate to call me on 0401 009 617.

Kind regards
Matt

Share

[addtoany]

Read Next

The Fitz, North Perth – Project Update April 2016

Development ProjectsThe Fitz Apartments

Get the latest insights and sign up 

Need more information?

Whether you’re investing, building, or need property support, we are here to guide you through every step of your property journey.