Anzac Road, Mount Hawthorn – July Update 2020

During July the four rear townhouses had their roof frames completed and sheeting of their roofs has commenced. The two front townhouses saw the completion of their brickwork, lightweight internal walls and roof framing. Their roofs will be sheeted after the completion of the rear four townhouses.

As soon as the roof sheeting is completed the builder will focus on getting the townhouses watertight so they can commence works inside the townhouses, in particular the floating of the internal walls.

I look forward to updating you next month, however, should you have any queries in the meantime please do not hesitate to contact me on (08) 6144 0700 or 0451 533 440.

Regards,
Travis McKenzie

 

Share

[addtoany]

Read Next

Second round of Government First Home Loan Deposit Scheme has kicked off

FinanceFirst Home Buyers

Get the latest insights and sign up 

Need more information?

Whether you’re investing, building, or need property support, we are here to guide you through every step of your property journey.