4 Downey Drive, Manning – Project Update February 2018

During February the ground floor brickwork for units 3, 4 & 5 was completed up to the first floor slab level.  This then allowed the formwork for their first floor slabs to be constructed.  Once completed, the electricians laid their conduits and canisters and the plumbers set out their penetrations and collars.  The reo was then installed in preparation for the concrete pour in the coming days.

After the bricklayers had completed the ground floors of units 3, 4 & 5 they then moved onto units 1 and 2 where they are very close to reaching the first floor slab level.

Construction is currently on schedule with practical completion anticipated for December this year.

I look forward to updating you next month, but should you have any queries in the meantime, or would like to talk to one of our sales agents about securing one of the apartments or townhouses, please do not hesitate to contact me on (08) 6144 0700 or 0451 533 440.

 

Regards,

Travis McKenzie

Share

[addtoany]

Read Next

121 Bank Street, East Victoria Park – Project Update February 2018

121 Bank StreetDevelopment Projects

Get the latest insights and sign up 

Need more information?

Whether you’re investing, building, or need property support, we are here to guide you through every step of your property journey.