Vic Quarter – Project Update June 2018

Despite the wettest June in Perth for 6 years, good progress was made on site this month. Bulk excavation is now completed and only one section of basement slab remains to be poured. The ground floor slabs only have two sections remaining which will be poured this weekend. The plumbing and electrical pre-lays are completed in the basement level and the mechanical extraction equipment will be delivered to site tomorrow to begin installation.

On the ground floor half the concrete columns have now been formed and poured and the AFS wall installation has begun. Work will commence shortly on the formwork for the first floor slab.

We look forward to updating you as construction progresses, but if you have any questions, please don’t hesitate to call me directly on (08) 6144 0700 or 0401 009 617.

Regards,
Matt Evans

 

 

Share

[addtoany]

Read Next

4 Downey Drive, Manning – Project Update June 2018

4 Downey DriveDevelopment Projects

Get the latest insights and sign up 

Need more information?

Whether you’re investing, building, or need property support, we are here to guide you through every step of your property journey.